Construction Update: February 3, 2025
Since our last monthly update, crews have continued to clear and grade the site, demo near the stairwell and cloister, and pour concrete footers and basement walls. And, the relocated Preschool playground is complete.
In the coming month, our contractor Holder Construction will begin pouring slabs on grade, waterproofing the basement walls, and erecting steel to frame the chapel. A mobile crane will be placed on site soon too.
A word on safety—we have noticed neighbors walking up the Andrews Driveway during construction. On weekdays, the driveway is considered an active construction site and not safe for pedestrians. Please utilize the stone path behind the Lanier House to access Andrews Drive during the week. Thank you!