Construction Update: April 2, 2025
In the past month, the main level and balcony level steel has been erected—including the window arches and framing! Foundation and basement wall waterproofing has also been completed and much of the decking has been installed on the main level. Behind the scenes, new boilers have been delivered and production of the oculus has commenced.
In the coming month, steel work will continue. Additional grading will take place and masonry on the foundation walls will also begin.